This past week has been a blur of activity at the house. They got the front door installed and the garage doors on, so we can now lock up the place at the end of the day. They finished up the HVAC and furnace and started the electric installation. Enjoy the pictures!
Last Thursday, Day 38. They installed garage doors and the front door.
We're still waiting on the Transom Window that goes over the front door. Hopefully that will be in next week.
They strarted running all the wiring for our electrical outlets and switches.
Lindsey and Carl stopped by to make sure the electricians got everything in the right place. We made a few adjustments, and everything is looking great.
The Kitchen (below) looks packed full of blue boxes! We'll have lots of light and plenty of places to plug in all of Lindsey's kitchen gadgets.
They finally finished installing the furnace and all of the heating vents.
The house is definitely going up fast. The electric should be done by next Monday. The plumbers are coming next week to install all the pipes. Insulation goes in after that and the builders should be working on drywall by the middle of April. We're hoping to move in by June. Stay tuned for more pictures this week and next.